Shewalton WWPS

Client

WGM / Scottish Water

Duration

8 Weeks

Project Overview

A&L MEICA was commissioned to undertake significant upgrades at the Shewalton Waste Water Pumping Station in Irvine, Scotland on behalf of WGM and Scottish Water. The project involved replacing the existing DN 500 pipework within the drywell, 2 x 180kw Xylem macerating pumps and 2 x  DN 500 non-return valves.

The station is crucial for wastewater management, pumping sewage from lower to higher elevations to facilitate continuous and cost-effective treatment; A single inlet feeds into a wet well, which then supplies the drywell pumps that drive the rising main.

Works Detail

Key Achievements

  • Extensive Fabrication: Both lines required rotation by 11 degrees, necessitating extensive fabrication, including two transition pieces and a 90-degree feed to the suction side of the pump.
  • Successful Refurbishment: The refurbishment was made viable through these modifications.

 

Challenges Faced

  • Location: The site was approximately 10 metres below ground level in a potentially explosive environment and confined space.
  • Structural Modifications: Existing steelwork, support beams, and access platforms had to be altered to facilitate the works.
  • Material Access: Access was via a 2-metre square void, requiring intricate lifting procedures and manual mechanised methods due to the unsuitability of the overhead crane.

 

Innovative Solutions

  • Manual Lifting Methods: Utilised A-frames, chain blocks, and hoists for lifting operations.
  • Intricate Lifting Procedures: Implemented detailed lifting plans to manoeuvre the new vertical pipe riser and install a new tied flange to interface with existing pipework.

 

Stakeholder Involvement

  • Client PRC: Jordan Davidson
  • A&L Project Manager : Tom Miller
  • Site Supervisor: Ross Cowan
  • Design and Site Management: WGM Engineering
  • Lifting Operations: WGM / A&L

 

Environmental and Safety Measures

  • DSEAR Compliance: Forced ventilation and extraction to mitigate risks in the potentially explosive environment.
  • Confined Space Management: Monitoring and management of warm temperatures and physical hazards within the confined space.

 

Lessons Learnt

  • Early Involvement: Offering specialist services at the design stage to avoid unforeseen issues.
  • Quality Welding: External NDT testers praised the welding quality, noting it as some of the best they had ever seen.

 

Additional Notes

Both the A&L site and fabrication teams delivered excellent outcomes for the client despite challenging timescales, environments, and working conditions.

Contact Us

Our support team are here to help with your enquiry. Please contact us today to discuss your requirements with one of our friendly members of staff.